Updates

National Energy Board Update – September 7, 2018

By IAMC-Line 3 / September 7, 2018 /

  Construction and Compliance Update: Construction activity is occurring on all spreads and facilities. Please refer to Construction Progress Reports for details (below). On 6 September 2018, Enbridge notified the Board that it will employ a contingency crossing method at the Oak Creek # 1 watercourse crossing (A93908). On 31 August 2018, Enbridge filed updated…

Read More

National Energy Board update – August 24, 2018

By IAMC-Line 3 / August 24, 2018 /

    Environmental Alignment Sheets On 15 August 2018, the Board issued a Letter to Enbridge, approving updated Environmental Alignment Sheets, pursuant to Condition 6 of OC-63. Enbridge provided the NEB with the updated Environmental Alignment Sheets on 23 July 2018 (A93213).  The company indicated that the revisions were due to ongoing review, sampling results…

Read More